Thursday, November 13

It's still fall right?!?

On the bright side, the unseasonably cold temperatures seem to make everyone work just a little faster.  ProPump and Controls, Liebold Irrigation and your maintenance staff are working hard to tie up all of our fall projects as well as putting the finishing touches on our new irrigation source/pump station/range house.  All the while, we are still grinding away on #14.  We have never been so busy in November, and we love it!

"Project Water" (sounds better than 'water project' to me) is moving along nicely.  ProPump and Controls/Liebold Irrigation are installing our new main lines and doing battle with the bedrock on the driving range.  There's been digging, welding, grinding, and every manner of physical labor involved to get that new pipe in the ground.  Our electrician has been busy with staging materials and there has even been a Toledo Edison sighting as they decided to finally install our new transformer and pull the remainder of our underground supply line.

Carl, "The Wizard" prepping our well heads for new hardware.
The new valve assembly goes on.  The pumps have still not been installed, but we are trying to get the infrastructure set asap.
Custom fixtures for our main line drops.
The trench line headed to the new range/pump house.  

When you work with one of the most highly regarded irrigation companies in the world, you get a really nice result.  Trench backfilled, compacted, sod laid and cleaned.  Pretty clean result for the amount of disruption burying a 10 inch pipe over 2 feet below the surface.
Carl started work setting the portion of the main line that will run through the pump station.
By day four they were digging on well #2.  Here comes the bedrock.......
A little in the field metal work getting the custom pipes just right.
Even Toledo Edison made an appearance to install our new transformer and pull the remainder of the underground supply line.
While all of this is going on, we have been busy trying to get #14 as close to done as we can before everything decides to freeze.  There is finish work, bunker sand placement, drainage work, and cleanup to do before the bitter cold comes next week.

Getting the drainage installed for the front bunker.  The last of the three to be drained.  Hope to get finished and dump sand in tomorrow.
With the depth of the bunker, we had to trench pretty far to get the necessary fall needed to drain the bunker.  A perfect example of how many corners were cut in the construction of the golf course over the years.  Nobody wanted to handle this much work to do things right before.  Now it is done and done correctly.
The back left bunker finally getting filled.
A little fine tuning and compacting.  We are pushing the sand up to the edges of the sod to protect against dessication.
Also, you may notice a fresh sand topdressing on the greens.  With colder temperatures approaching fast, we wanted to ensure we could get some protection down before the ground freezes.  If there is another day of golf available before we put out temporary cups, we will make it as playable as possible.

Overall great progress despite the weather.  Very pleased thus far but still a long way to go.

Further updates as events warrant.

No comments:

Post a Comment